Direct answer
Commissioning should prove that the installed machine is complete, connected correctly, safe to test and capable of producing acceptable packs under site conditions. Work from installation and utility checks through functions, safeguards, dry cycles, product trials, performance, training and handover.
Key takeaways
- Define the boundary between installation, commissioning and acceptance.
- Verify installation and utilities before functional testing.
- Progress from dry functions to representative production.
- Complete training, documents and open-action closure.
Set a measurable objective
The team should know which tests release energy, which introduce product and which form contractual SAT evidence. Identify who can authorise each stage and how defects are controlled.
- Reference the approved layout and requirement
- List commissioning and SAT responsibilities
- Define test products, packs and quantities
- Agree production-release authority
Measure the current production condition
Check level, anchoring, services, earthing, pressure, flow, network, guards, access and interfaces. Record values rather than relying on visual completion.
- Inspect transport damage and assembly
- Verify electrical and pneumatic connections
- Test emergency stops, guards and safety circuits
- Confirm software, recipes and backups
Plan the work in a controlled sequence
Test manual modes, sensors, actuators, alarms, blocked and starved states before adding product. Introduce materials under controlled settings and record quality and output.
- Challenge no-product/no-pack conditions
- Test rejects and fault recovery
- Run minimum, maximum and hardest formats
- Record sustained good output and interventions
Hold the improvement after handover
Handover should include manuals, drawings, software backups, settings, spares, maintenance, training records and an agreed action list. Temporary settings or bypasses must not become normal production.
- Approve recipes and changeover standards
- Train operators and maintenance personnel
- Close or formally manage outstanding actions
- Sign production release and acceptance separately
Comparison table
| Stage | Customer decision | Evidence |
|---|---|---|
| Objective | Define the boundary between installation, commissioning and acceptance. | A numerical target and owner |
| Baseline | Verify installation and utilities before functional testing. | Representative production records |
| Action | Progress from dry functions to representative production. | A timed plan with responsibilities |
| Control | Complete training, documents and open-action closure. | Approved standard work and review data |
Free working templates
Download these files and adapt them to the actual machine, product, site and acceptance plan.
Related buyer guides and tools
Relevant machinery and support routes
Use the guide to define the requirement, then compare the specialist routes below against representative product, packaging and output evidence.
